Corporate

Hayes-Yorktown 230kV Line

Hayes-Yorktown Line - click to enlarge. 

To ensure that residents in the Middle Peninsula area have continued reliable electric service, Dominion Virginia Power has been approved to build a new 230,000-volt (230 kV) transmission line to serve Gloucester and interconnect the Middle Peninsula area. (Refer to Approval Process below for details.)

The new transmission line will extend from Dominion's Yorktown Power Station under the York River for approximately 3.5 miles to Gaines Point, where Dominion will construct an underground-to-overhead transition station. From there, the line will continue overhead along existing right-of-way for approximately 3.9 miles to the Hayes Substation.

Project Details

Construction Schedule

Summer 2010

  • SCC issued Final Order approving project.

Fall 2010

  • Preconstruction activities began, including right-of-way clearing and site preparation.

Winter 2010

  • Temporary pylons placed in the York River to accommodate crane platforms.
  • Drill rigs brought in and assembled on both sides of the river.
  • Drilling began in February on both sides of the river.

Spring 2011

  • Soil sample boring along overhead right-of-way began.
  • Began drilling for underwater pipe.

Summer 2011

  • Underwater activity continued in the York River.
  • Pulled approximately 7000 ft of welded pipe from the northern shore (Gloucester) to the platform located in the York River.
  • Installation of manhole covers completed on the southern shore (Yorktown).
  • Bore work began on the southern shore (Yorktown).

Fall/Winter 2011

  • Completed pulling pipe from the northern shore (Gloucester) to the platform located in the York River.
  • Foundation installation for overhead transmission line to begin in Gloucester.
  • Begin construction of Gaines Point Transition Station.

Summer 2012

  • Energize new transmission line.

Click to enlarge.Construction on the York River - click to enlarge.

Route Map
  • View a route map of the Hayes-Yorktown line.
Need For the Project

The Gloucester area is presently served by a single, long transmission line (115 kV) that extends southward from our Harmony Village Substation. This new line provides a second feed for the Hayes Substation (redundant source), and creates a network loop of the Dominion facilities in the area, for greater system reliability.

Project Details
  • Approximate total line length: 7.4 miles
  • Approximate overhead right-of-way width: 100 feet
  • Typical structure description: single pole
  • Approximate underwater cable length: 3.5 miles
Approval Process

The State Corporation Commission (SCC) is responsible for determining the need, route and environmental impact of transmission lines at 138kV and above in Virginia. The company filed an SCC application for the Hayes - Yorktown 230 kV Transmission Line on July 1, 2009.

In September 2009, the SCC issued an Order for Notice and Hearing prescribing notice of the application, establishing the procedural schedule for the case and appointing a Hearing Examiner to conduct all further proceedings on the matter on behalf of the SCC and issue a report. The Hearing Examiner for the case then issued a Ruling that extended some of the procedural dates initially established by the Order for Notice and Hearing.

A public hearing on the application was held on February 9, 2010, in the Commission's Courtroom in Richmond, Virginia, to receive the testimony of public witnesses and the evidence provided by Dominion, any Respondents, and the Commission Staff.

In May, the Hearing Examiner filed her Report recommending that the SCC grant Dominion a Certificate of Public Convenience and Necessity for the Hayes-Yorktown project.

On June 18, 2010, the State Corporation Commission issued its Final Order, granting a Certificate of Public Convenience and Necessity for the project and requiring construction to be completed within 24 months from the date of the Order. On page 7 of the Final Order, the Commission agrees with the Hearing Examiner in finding that "the record establishes that the proposed transmission line is necessary to assure that the Company can continue to provide reliable service to the Middle Peninsula area" and that "the proposed project will have minimal adverse impact on scenic assets, historic districts, and the environment."  

Additional information and documents pertaining to this case may be found by referencing Case No. PUE-2009-00049, after following the instructions available at the Commission's website: http://www.scc.virginia.gov/case.

Contact Us

Contact us if you have questions or concerns about the Hayes-Yorktown project.

Questions and Answers

Will Dominion require additional right-of-way?

No, the proposed transmission line will be constructed within an existing right-of-way. Dominion obtained the necessary easements and acquired property for these new facilities in the late 1980s.

Will additional clearing be necessary for this line?

Yes, for the overhead portion of the line, the existing 100’ wide right-of-way will need to be cleared before construction begins and some danger trees will need to be removed. Danger trees are trees outside the right-of-way that are tall enough to potentially impact the transmission line. Trees are cut to be no more than 3 inches above ground level. Debris that is adjacent to homes will be disposed of by chipping or removal. In other areas, debris may be mulched or chipped as practicable. Clearing will be accomplished by hand in wetland areas and within 100 feet of streams. Care will be taken not to leave debris in streams or wetland areas. Matting will be used for heavy equipment in these areas. Erosion control devices will be used on an ongoing basis during all clearing activities.

Will Dominion repair damage due to construction?

Yes. Our easement agreements allow us access to private roads of property owners crossed by the right of way. The company, at its expense, will repair any private roads damaged by Dominion or its contractors during construction of the line or during future maintenance. In addition, we will reimburse property owners for crop damage, and repair or replace fences or gates if we should damage them.

How will the completion of this project benefit me as a resident?

This new transmission line and related improvements at the Hayes substation will ensure that residents in the Middle Peninsula area have continued reliable electric service. This new line provides a second feed for the Hayes Substation (redundant source), and creates a network loop of the Dominion facilities in the area, for greater system reliability. As a resident, this means fewer outages, and shorter durations when the lights do go out.

Can you build the entire line underground?

Overhead (OH) lines have proven to be the best choice for providing safe, reliable and economical power to our customers. Dominion operates a high-voltage network of approximately 6,100 miles of transmission lines. Of this total, less than 1% (52 miles) is comprised of underground (UG) cables. At 230 kV, there are approximately 2400 miles of OH lines and 34 miles of UG cables. These installations are primarily for large water crossings, dense metro areas, or other areas that are not suitable for overhead lines.

Underground transmission lines are not as desirable from an operational point of view. The duration of outages for underground transmission lines is significantly greater compared to overhead lines due to the complexities of locating failures and facilitating repairs. (We are installing extra cables under the York River to help address this issue.) Additionally, labor and material costs for the installation of a 230 kV underground transmission line would be 8 to 10 times more expensive than an overhead option, and these costs are passed on to our customers.

The extensive wetlands through this area present another challenge. Underground installation would be more environmentally invasive than placing overhead structures.

What will be the environmental impact of construction for the overhead line?

As part of the SCC application, Dominion completes an evaluation of potential environmental, cultural, and historical impacts of the project. Dominion works with many local and state agencies to complete these evaluations and mitigate any impacts. The company also submits annual Erosion and Sedimentation Control Specifications for the construction and maintenance of transmission lines to the Virginia Department of Conservation and Recreation for review and approval. This project will be submitted for approval prior to construction. Our contractors receive copies of the E&S specifications and any additional permit conditions prior to construction and are directed to meet any requirements. The right-of-way will be rehabilitated when construction is complete.

Should I be concerned about Electric and Magnetic Fields?

Dominion is sensitive to public concern about possible health effects from exposure to electric and magnetic fields (EMF). We continually monitor EMF research and speak to our customers and employees regularly to share the latest information available. The Virginia Department of Health, in its final report of EMF research said:

"Based on the review and analysis of the exhaustive literature review and other research projects completed under the EMF-RAPID program, the Virginia Department of Health is of the opinion that there is no conclusive and convincing evidence that exposure to extremely low frequency EMF emanated from nearby high voltage transmission lines is causally associated with an increased incidence of cancer or other detrimental health effects in humans. Even if it is assumed that there is an increased risk of cancer as implied in some epidemiologic studies, the empirical relative risk appears to be fairly small in magnitude and the observed association appears to be tenuous. The studies published in the literature lack clear demonstration of a cause and effect relationship as well as a definitive dose-response gradient."

Additional information is available in the following links:

Where may I obtain more information on the project?

More information is available in the SCC application filed by the company on July 1, 2009 for the Hayes - Yorktown 230 kV Transmission Line. The SCC also maintains copies of documents filed in the case. They are available online at www.scc.virginia.gov/case. Refer to Case No. PUE-2009-00049.

NYSE : (May 18, 2012) D 52.29 0.40